A.4.7.1.1 - Pengikisan/pengerokan 1 M2 permukaan cat lama

A.4.7.1.1 - Pengikisan/pengerokan 1 M2 permukaan cat lama
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1500 81.500,00 12.225,00
Mandor OH 0,0030 107.000,00 321,00
JUMLAH HARGA TENAGA 12.546,00
B BAHAN
Soda api Kg 0,0500 20.000,00 1.000,00
JUMLAH HARGA BAHAN 1.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 13.546,00
E Overhead & Profit 10% x D 1.354,60
F HARGA SATUAN   PEKERJAAN ( D + E )    14.900,60