Skip to content
A.4.7.1.10 - Pengecatan 1M2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
A.4.7.1.10 - Pengecatan 1M2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,0200 |
81.500,00 |
1.630,00 |
|
Tukang cat |
OH |
0,0630 |
96.500,00 |
6.079,50 |
|
Kepala tukang |
OH |
0,0063 |
107.000,00 |
674,10 |
|
Mandor |
OH |
0,0030 |
107.000,00 |
321,00 |
|
|
|
JUMLAH HARGA TENAGA |
8.704,60 |
B |
BAHAN |
|
|
|
|
|
Plamuur |
Kg |
0,1000 |
25.000,00 |
2.500,00 |
|
Cat dasar |
Kg |
0,1000 |
24.000,00 |
2.400,00 |
|
Cat penutup |
Kg |
0,2600 |
24.000,00 |
6.240,00 |
|
|
|
JUMLAH HARGA BAHAN |
11.140,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
19.844,60 |
E |
Overhead & Profit |
10% x D |
|
|
1.984,46 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
21.829,06 |