Skip to content Skip to sidebar Skip to footer

A.4.7.1.11 - Pengecatan 1 M2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)

A.4.7.1.11 - Pengecatan 1 M2 tembok lama ( 1 lapis cat dasar, 2   lapis cat penutup)
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0280 81.500,00 2.282,00
Tukang cat OH 0,0420 96.500,00 4.053,00
Kepala tukang OH 0,0042 107.000,00 449,40
Mandor OH 0,0030 107.000,00 321,00
JUMLAH HARGA TENAGA 7.105,40
B BAHAN
Cat dasar Kg 0,1200 24.000,00 2.880,00
Cat penutup Kg 0,1800 24.000,00 4.320,00
JUMLAH HARGA BAHAN 7.200,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 14.305,40
E Overhead & Profit 10% x D 1.430,54
F HARGA SATUAN   PEKERJAAN ( D + E )    15.735,94