A.4.7.1.20 - Pengecatan 1 M2 permukaan baja galvanis secara manual sistem 3 lapis
A.4.7.1.20 - Pengecatan 1 M2 permukaan baja galvanis secara manual sistem 3 lapis | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,4000 | 81.500,00 | 32.600,00 | |
Tukang cat | OH | 0,8000 | 96.500,00 | 77.200,00 | |
Kepala tukang | OH | 0,0800 | 107.000,00 | 8.560,00 | |
Mandor | OH | 0,0200 | 107.000,00 | 2.140,00 | |
JUMLAH HARGA TENAGA | 120.500,00 | ||||
B | BAHAN | ||||
Cat dasar | Kg | 0,1100 | 65.000,00 | 7.150,00 | |
Cat antara | Kg | 0,1700 | 65.000,00 | 11.050,00 | |
Cat penutup | Kg | 0,0800 | 65.000,00 | 5.200,00 | |
Kwas | Bh | 0,0100 | 7.500,00 | 75,00 | |
Pengencer | Ltr | 0,0100 | 27.500,00 | 275,00 | |
JUMLAH HARGA BAHAN | 23.750,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 144.250,00 | ||
E | Overhead & Profit | 10% x D | 14.425,00 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 158.675,00 |