A.4.7.1.9 - Pelaburan 1 M2 bidang kayu dengan vernis
A.4.7.1.9 - Pelaburan 1 M2 bidang kayu dengan vernis |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,1600 |
81.500,00 |
13.040,00 |
|
Tukang cat |
OH |
0,1600 |
96.500,00 |
15.440,00 |
|
Kepala tukang |
OH |
0,0160 |
107.000,00 |
1.712,00 |
|
Mandor |
OH |
0,0030 |
107.000,00 |
321,00 |
|
|
|
JUMLAH HARGA TENAGA |
30.513,00 |
B |
BAHAN |
|
|
|
|
|
Vernis |
Ltr |
0,1500 |
80.000,00 |
12.000,00 |
|
Dempul |
Kg |
0,0500 |
15.000,00 |
750,00 |
|
Ampelas |
Lbr |
0,1000 |
5.000,00 |
500,00 |
|
|
|
JUMLAH HARGA BAHAN |
13.250,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
43.763,00 |
E |
Overhead & Profit |
10% x D |
|
|
4.376,30 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
48.139,30 |