Skip to content
A.5.1.1.2 - Pemasangan 1 Buah closet jongkok porslen
A.5.1.1.2 - Pemasangan 1 Buah closet jongkok porslen |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,0000 |
81.500,00 |
81.500,000 |
|
Tukang batu |
OH |
1,5000 |
96.500,00 |
144.750,000 |
|
Kepala tukang |
OH |
0,1500 |
107.000,00 |
16.050,000 |
|
Mandor |
OH |
0,1600 |
107.000,00 |
17.120,000 |
|
|
|
JUMLAH HARGA TENAGA |
259.420,000 |
B |
BAHAN |
|
|
|
|
|
Closet jongkok |
Unit |
1,0000 |
150.000,00 |
150.000,000 |
|
Semen Portland |
Kg |
6,0000 |
1.250,00 |
7.500,000 |
|
Pasir pasang |
M3 |
0,0100 |
350.000,00 |
3.500,000 |
|
|
|
JUMLAH HARGA BAHAN |
161.000,000 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
420.420,000 |
E |
Overhead & Profit |
10% x D |
|
|
42.042,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
462.462,00 |
======= ARTIKEL TERKAIT =======
Post a Comment for "A.5.1.1.2 - Pemasangan 1 Buah closet jongkok porslen"