A.5.1.1.2 - Pemasangan 1 Buah closet jongkok porslen

A.5.1.1.2 - Pemasangan 1 Buah closet jongkok porslen
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 1,0000 81.500,00 81.500,000
Tukang batu OH 1,5000 96.500,00 144.750,000
Kepala tukang OH 0,1500 107.000,00 16.050,000
Mandor OH 0,1600 107.000,00 17.120,000
JUMLAH HARGA TENAGA 259.420,000
B BAHAN
Closet jongkok Unit 1,0000 150.000,00 150.000,000
Semen Portland Kg 6,0000 1.250,00 7.500,000
Pasir pasang M3 0,0100 350.000,00 3.500,000
JUMLAH HARGA BAHAN 161.000,000
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 420.420,000
E Overhead & Profit 10% x D 42.042,00
F HARGA SATUAN   PEKERJAAN ( D + E )    462.462,00