NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 3,3000 81.500,00 268.950,00
Tukang batu OH 1,1000 96.500,00 106.150,00
Kepala tukang OH 0,0100 107.000,00 1.070,00
Mandor OH 0,1600 107.000,00 17.120,00
JUMLAH HARGA TENAGA 393.290,00
B BAHAN
Closet duduk Unit 1,0000 1.650.000,00 1.650.000,00
Perlengkapan Ls 6% x closet 99.000,00 99.000,00
JUMLAH HARGA BAHAN 1.749.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 2.142.290,00
E Overhead & Profit 10% x D 214.229,00
F HARGA SATUAN   PEKERJAAN ( D + E ) 2.356.519,00   