A.5.1.1.12 - Pemasangan 1 Buah bak cuci piring stainlessteel

A.5.1.1.12 - Pemasangan 1 Buah bak cuci piring stainlessteel
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0300 81.500,00 2.445,00
Tukang batu OH 0,3000 96.500,00 28.950,00
Kepala tukang OH 0,0300 107.000,00 3.210,00
Mandor OH 0,0150 107.000,00 1.605,00
JUMLAH HARGA TENAGA 36.210,00
B BAHAN
Bak cuci piring Unit 1,0000 550.000,00 550.000,00
Waterdrain Bh 1,0000 20.000,00 20.000,00
JUMLAH HARGA BAHAN 570.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 606.210,00
E Overhead & Profit 10% x D 60.621,00
F HARGA SATUAN   PEKERJAAN ( D + E )    666.831,00