A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½”
A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½” | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,0540 | 81.500,00 | 4.401,00 | |
Tukang batu | OH | 0,0900 | 96.500,00 | 8.685,00 | |
Kepala tukang | OH | 0,0090 | 107.000,00 | 963,00 | |
Mandor | OH | 0,0270 | 107.000,00 | 2.889,00 | |
JUMLAH HARGA TENAGA | 16.938,00 | ||||
B | BAHAN | ||||
Pipa galvanis medium A ½” | M | 1,2000 | 23.000,00 | 27.600,00 | |
Perlengkapan | Ls | 35%xpipa | 8.050,00 | 8.050,00 | |
JUMLAH HARGA BAHAN | 35.650,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 52.588,00 | ||
E | Overhead & Profit | 10% x D | 5.258,80 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 57.846,80 |
Post a Comment for "A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½”"