Skip to content Skip to sidebar Skip to footer

A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½”

A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½”
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0540 81.500,00 4.401,00
Tukang batu OH 0,0900 96.500,00 8.685,00
Kepala tukang OH 0,0090 107.000,00 963,00
Mandor OH 0,0270 107.000,00 2.889,00
JUMLAH HARGA TENAGA 16.938,00
B BAHAN
Pipa galvanis   medium A ½” M 1,2000 23.000,00 27.600,00
Perlengkapan Ls 35%xpipa 8.050,00 8.050,00
JUMLAH HARGA BAHAN 35.650,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 52.588,00
E Overhead & Profit 10% x D 5.258,80
F HARGA SATUAN   PEKERJAAN ( D + E )    57.846,80



======= ARTIKEL TERKAIT =======



Post a Comment for "A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½”"