A.5.1.1.21 - Pemasangan 1 M' pipa galvanis diameter 1”

A.5.1.1.21 - Pemasangan 1 M' pipa galvanis diameter 1”
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0540 81.500,00 4.401,00
Tukang batu OH 0,0900 96.500,00 8.685,00
Kepala tukang OH 0,0090 107.000,00 963,00
Mandor OH 0,0270 107.000,00 2.889,00
JUMLAH HARGA TENAGA 16.938,00
B BAHAN
Pipa galvanis   medium A 1” M 1,2000 45.000,00 54.000,00
Perlengkapan % 35,0000 15.750,00 15.750,00
JUMLAH HARGA BAHAN 69.750,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 86.688,00
E Overhead & Profit 10% x D 8.668,80
F HARGA SATUAN   PEKERJAAN ( D + E )    95.356,80