Skip to content Skip to sidebar Skip to footer

A.5.1.1.22 - Pemasangan 1 M' pipa galvanis diameter 1 ½”

A.5.1.1.22 - Pemasangan 1 M' pipa galvanis diameter 1 ½”
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1080 81.500,00 8.802,00
Tukang batu OH 0,1800 96.500,00 17.370,00
Kepala tukang OH 0,0180 107.000,00 1.926,00
Mandor OH 0,0050 107.000,00 535,00
JUMLAH HARGA TENAGA 28.633,00
B BAHAN
Pipa galvanis (   1½" ) M 1,2000 70.000,00 84.000,00
Perlengkapan % 35,0000 24.500,00 24.500,00
JUMLAH HARGA BAHAN 108.500,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 137.133,00
E Overhead & Profit 10% x D 13.713,30
F HARGA SATUAN   PEKERJAAN ( D + E )    150.846,30