A.5.1.1.24 - Pemasangan 1 M' pipa galvanis diameter 4”
A.5.1.1.24 - Pemasangan 1 M' pipa galvanis diameter 4” | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,1350 | 81.500,00 | 11.002,50 | |
Tukang batu | OH | 0,2250 | 96.500,00 | 21.712,50 | |
Kepala tukang | OH | 0,0230 | 107.000,00 | 2.461,00 | |
Mandor | OH | 0,0070 | 107.000,00 | 749,00 | |
JUMLAH HARGA TENAGA | 35.925,00 | ||||
B | BAHAN | ||||
Pipa galvanis 4” | M | 1,2000 | 225.000,00 | 270.000,00 | |
Perlengkapan | % | 35,0000 | 78.750,00 | 78.750,00 | |
JUMLAH HARGA BAHAN | 348.750,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 384.675,00 | ||
E | Overhead & Profit | 10% x D | 38.467,50 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 423.142,50 |