Skip to content Skip to sidebar Skip to footer

A.5.1.1.25a - Pemasangan 1 M' Pipa PVC SNI 06-0084-2002/ Standar ISO 4422, S -10 (10 bar) diameter 1/2”

A.5.1.1.25a - Pemasangan 1 M' Pipa PVC SNI 06-0084-2002/ Standar   ISO 4422, S -10 (10 bar) diameter 1/2”
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0360 81.500,00 2.934,00
Tukang batu OH 0,0600 96.500,00 5.790,00
Kepala tukang OH 0,0060 107.000,00 642,00
Mandor OH 0,0020 107.000,00 214,00
JUMLAH HARGA TENAGA 9.580,00
B BAHAN
Pipa PVC 1/2” M 1,2000 5.500,00 6.600,00
Perlengkapan % 35,0000 1.925,00 1.925,00
JUMLAH HARGA BAHAN 8.525,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 18.105,00
E Overhead & Profit 10% x D 1.810,50
F HARGA SATUAN   PEKERJAAN ( D + E )    19.915,50



======= ARTIKEL TERKAIT =======



Post a Comment for "A.5.1.1.25a - Pemasangan 1 M' Pipa PVC SNI 06-0084-2002/ Standar ISO 4422, S -10 (10 bar) diameter 1/2”"