A.5.1.1.35 - Pemasangan 1 M' pipa beton diameter 15 – 20 cm

A.5.1.1.35 - Pemasangan 1 m’ pipa beton diameter 15 – 20 cm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1400 81.500,00 11.410,00
Tukang batu OH 0,0700 96.500,00 6.755,00
Kepala tukang OH 0,0070 107.000,00 749,00
Mandor OH 0,0070 107.000,00 749,00
JUMLAH HARGA TENAGA 19.663,00
B BAHAN
Pipa tanah dia 15 Bh 1,1000 65.000,00 71.500,00
Bata merah M3 0,0270 600,00 16,20
Semen portlan Kg 3,9200 1.250,00 4.900,00
Pasir pasang M3 0,0560 350.000,00 19.600,00
Pasir urug M3 0,0240 220.000,00 5.280,00
JUMLAH HARGA BAHAN 101.296,20
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 120.959,20
E Overhead & Profit 10% x D 12.095,92
F HARGA SATUAN   PEKERJAAN ( D + E )    133.055,12