A.5.1.1.4 - Pemasangan 1 Buah urinoir

A.5.1.1.4 - Pemasangan 1 Buah urinoir
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 1,0000 81.500,00 81.500,00
Tukang batu OH 1,0000 96.500,00 96.500,00
Kepala tukang OH 0,1000 107.000,00 10.700,00
Mandor OH 0,0500 107.000,00 5.350,00
JUMLAH HARGA TENAGA 194.050,00
B BAHAN
Urinoir Unit 1,0000 1.300.000,00 1.300.000,00
Semen Portland Kg 6,0000 1.250,00 7.500,00
Pasir pasang M3 0,0100 350.000,00 3.500,00
Perlengkapan % 30,0000 390.000,00 390.000,00
JUMLAH HARGA BAHAN 1.701.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1.895.050,00
E Overhead & Profit 10% x D 189.505,00
F HARGA SATUAN   PEKERJAAN ( D + E ) 2.084.555,00   