A.5.1.1.4 - Pemasangan 1 Buah urinoir
A.5.1.1.4 - Pemasangan 1 Buah urinoir |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,0000 |
81.500,00 |
81.500,00 |
|
Tukang batu |
OH |
1,0000 |
96.500,00 |
96.500,00 |
|
Kepala tukang |
OH |
0,1000 |
107.000,00 |
10.700,00 |
|
Mandor |
OH |
0,0500 |
107.000,00 |
5.350,00 |
|
|
|
JUMLAH HARGA TENAGA |
194.050,00 |
B |
BAHAN |
|
|
|
|
|
Urinoir |
Unit |
1,0000 |
1.300.000,00 |
1.300.000,00 |
|
Semen Portland |
Kg |
6,0000 |
1.250,00 |
7.500,00 |
|
Pasir pasang |
M3 |
0,0100 |
350.000,00 |
3.500,00 |
|
Perlengkapan |
% |
30,0000 |
390.000,00 |
390.000,00 |
|
|
|
JUMLAH HARGA BAHAN |
1.701.000,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
1.895.050,00 |
E |
Overhead & Profit |
10% x D |
|
|
189.505,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
2.084.555,00 |