Skip to content Skip to sidebar Skip to footer

A.6.1.1.9 - Pasang Paving Segitiga kecil Tebal 8 cm (K.300)

A.6.1.1.9 - Pasang Paving Segitiga kecil Tebal 8 cm (K.300)
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,2000 81.500,00 16.300,00
Tukang Batu OH 0,3000 96.500,00 28.950,00
Kepala Tukang OH 0,0300 107.000,00 3.210,00
Mandor OH 0,0250 107.000,00 2.675,00
JUMLAH HARGA TENAGA 51.135,00
B BAHAN
Paving Block K.300 M2 1,0100 128.000,00 129.280,00
Pasir Urug M3 0,0600 220.000,00 13.200,00
Pasir Pasang M3 0,0100 350.000,00 3.500,00
JUMLAH HARGA BAHAN 145.980,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 197.115,00
E Overhead & Profit 10% x D 19.711,50
F HARGA SATUAN   PEKERJAAN ( D + E )    216.826,50



======= ARTIKEL TERKAIT =======



Post a Comment for "A.6.1.1.9 - Pasang Paving Segitiga kecil Tebal 8 cm (K.300) "