A.4.4.2.23 - Pemasangan 1 M2 plesteran ciprat 1SP : 2PP

A.4.4.2.23 - Pemasangan 1 M2 plesteran ciprat 1SP : 2PP
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,3000 81.500,00 24.450,00
Tukang Batu OH 0,1000 96.500,00 9.650,00
Kepala Tukang OH 0,0100 107.000,00 1.070,00
Mandor OH 0,0150 107.000,00 1.605,00
JUMLAH HARGA TENAGA 36.775,00
B BAHAN
Portland Cement Kg 4,3200 1.250,00 5.400,00
Pasir Pasang M3 0,0060 350.000,00 2.100,00
JUMLAH HARGA BAHAN 7.500,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 44.275,00
E Overhead & Profit 10% x D 4.427,50
F HARGA SATUAN   PEKERJAAN ( D + E )    48.702,50