T.07.b.1 - 1 M3 Galian tanah berbatu sedalam < 1 m
T.07.b.1 - 1 M3 Galian tanah berbatu sedalam < 1 m | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
1 | Pekerja | OH | 0,4300 | 81.500,00 | 35.045,00 |
2 | Mandor | OH | 0,0430 | 115.000,00 | 4.945,00 |
JUMLAH HARGA TENAGA | 39.990,00 | ||||
B | BAHAN | ||||
BBM non subsidi | Liter | 1,2500 | 9.850,00 | 12.312,50 | |
JUMLAH HARGA BAHAN | 12.312,50 | ||||
C | Peralatan | ||||
1 | Jack hammer ** | Sewa-Hari | 0,1250 | 360.000,00 | 45.000,00 |
JUMLAH HARGA ALAT | 45.000,00 | ||||
D | Jumlah | (A+B+C) | 97.302,50 | ||
E | Overhead & Profit | 10% x D | 9.730,25 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 107.032,75 | ||
** Jika dilaklukan tanpa menggunakan peralatan, maka harga satuan diberi nilai 0 |