T.08.b.1 - 1 M3 Galian batu sedalam < 1 m
T.08.b.1 - 1 M3 Galian batu sedalam < 1 m | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
1 | Pekerja | OH | 1,0000 | 81.500,00 | 81.500,00 |
2 | Mandor | OH | 0,1000 | 115.000,00 | 11.500,00 |
JUMLAH HARGA TENAGA | 93.000,00 | ||||
B | BAHAN | ||||
BBM non subsidi | Liter | 2,5000 | 9.850,00 | 24.625,00 | |
JUMLAH HARGA BAHAN | 24.625,00 | ||||
C | ALAT | ||||
1 | Jack hammer ** | Sewa-Hari | 0,2500 | 360.000,00 | 90.000,00 |
JUMLAH HARGA ALAT | 90.000,00 | ||||
D | Jumlah | (A+B+C) | 207.625,00 | ||
E | Overhead & Profit | 10% x D | 20.762,50 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 228.387,50 | ||
** Jika dilaklukan tanpa menggunakan peralatan, maka harga satuan diberi nilai 0 |
Post a Comment for "T.08.b.1 - 1 M3 Galian batu sedalam < 1 m"