T.08.b.2 - 1 M3 Galian batu sedalam > 1 m s.d. 2 m

T.08.b.2 - 1 M3 Galian batu sedalam > 1 m s.d. 2 m
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
1 Pekerja OH 1,2000 81.500,00 97.800,00
2 Mandor OH 0,1200 115.000,00 13.800,00
JUMLAH HARGA TENAGA 111.600,00
B BAHAN
BBM non subsidi Liter 2,5000 9.850,00 24.625,00
JUMLAH HARGA BAHAN 24.625,00
C ALAT
1 Jack hammer ** Sewa-Hari 0,2500 360.000,00 90.000,00
JUMLAH HARGA ALAT 90.000,00
D Jumlah (A+B+C) 226.225,00
E Overhead & Profit 10% x D 22.622,50
F HARGA SATUAN PEKERJAAN ( D + E ) 248.847,50
** Jika dilaklukan   tanpa menggunakan peralatan, maka harga satuan diberi nilai 0