NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
1 Pekerja OH 1,3200 81.500,00 107.580,00
2 Mandor OH 0,1320 115.000,00 15.180,00
JUMLAH HARGA TENAGA 122.760,00
B BAHAN
BBM non subsidi Liter 2,5000 9.850,00 24.625,00
JUMLAH HARGA BAHAN 24.625,00
C ALAT
1 Jack hammer ** Sewa-Hari 0,2500 360.000,00 90.000,00
JUMLAH HARGA ALAT 90.000,00
D Jumlah (A+B+C) 237.385,00
E Overhead & Profit 10% x D 23.738,50
F HARGA SATUAN PEKERJAAN ( D + E ) 261.123,50