T.10.a.4 - 1 M3 Galian tanah lumpur > 3m, untuk setiap penambahan kedalaman 1 m
T.10.a.4 - 1 M3 Galian tanah lumpur > 3m, untuk setiap penambahan kedalaman 1 m |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
1 |
Pekerja |
OH |
0,1500 |
81.500,00 |
12.225,00 |
2 |
Mandor |
OH |
0,0150 |
115.000,00 |
1.725,00 |
|
|
|
JUMLAH HARGA TENAGA |
13.950,00 |
B |
BAHAN |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA BAHAN |
- |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
13.950,00 |
E |
Overhead & Profit |
10% x D |
|
|
1.395,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
15.345,00 |