T.11.a.2 - 1 M3 Galian pasir untuk pondasi bangunan sedalam > 1 m s.d 2m’ |
|
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
1 |
Pekerja |
OH |
0,8000 |
81.500,00 |
65.200,00 |
2 |
Mandor |
OH |
0,0800 |
115.000,00 |
9.200,00 |
|
|
|
JUMLAH HARGA TENAGA |
74.400,00 |
B |
BAHAN |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA BAHAN |
- |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
74.400,00 |
E |
Overhead & Profit |
10% x D |
|
|
7.440,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
81.840,00 |