T.14.a.3 - 1 M3 Timbunan tanah Padas
T.14.a.3 - 1 M3 Timbunan tanah Padas |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
1 |
Pekerja |
OH |
0,3300 |
81.500,00 |
26.895,00 |
2 |
Mandor |
OH |
0,0330 |
115.000,00 |
3.795,00 |
|
|
|
JUMLAH HARGA TENAGA |
30.690,00 |
B |
BAHAN |
|
|
|
|
1 |
Tanah Padas |
M3 |
1,2000 |
147.000,00 |
176.400,00 |
|
|
|
JUMLAH HARGA BAHAN |
176.400,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
207.090,00 |
E |
Overhead & Profit |
10% x D |
|
|
20.709,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
227.799,00 |