Perlu di ketahui, analisa Dihitung bukan Analisa SNI. Namun analisa perkiraan berdasarkan pengalaman pekerjaan dilapangan. Kemungkinan koefisien berbeda pada setiap lokasi pekerjaan. |
|
|
|
|
|
|
|
|
|
|
1 |
Ttk |
Instalasi Titik Lampu NYA 2x1x2,5mm dalam conduit high impact PVC 20 mm |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Pekerja |
|
0,0335 |
OH |
Rp 81.500,00 |
Rp 2.730,25 |
|
- |
Tukang Listrik |
|
0,3350 |
OH |
Rp 96.500,00 |
Rp 32.327,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 35.057,75 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Kabel NYA 1 x 2,5 Sqmm |
|
|
30,0000 |
M' |
Rp 4.100,00 |
Rp 123.000,00 |
|
- |
Pipa PVC 20 mm2 |
|
|
10,0000 |
M' |
Rp 3.000,00 |
Rp 30.000,00 |
|
- |
Material Bantu (Tdoos, sock, isolasi, dll) |
|
|
1,0000 |
Ls |
Rp 5.000,00 |
Rp 5.000,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 158.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 193.057,75 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 19.305,78 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 212.363,53 |
|
|
|
|
|
|
|
|
|
|
1 |
Ttk |
Instalasi Stop Kontak NYA 3x1x2,5mm dalam conduit high impact PVC 20 mm |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Pekerja |
|
0,0335 |
OH |
Rp 81.500,00 |
Rp 2.730,25 |
|
- |
Tukang Listrik |
|
0,3350 |
OH |
Rp 96.500,00 |
Rp 32.327,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 35.057,75 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Kabel NYA 1 x 2,5 Sqmm |
|
|
30,0000 |
M' |
Rp 4.100,00 |
Rp 123.000,00 |
|
- |
Pipa PVC 20 mm2 |
|
|
10,0000 |
M' |
Rp 3.000,00 |
Rp 30.000,00 |
|
- |
Material Bantu (Tdoos, sock, isolasi, dll) |
|
|
1,0000 |
Ls |
Rp 5.000,00 |
Rp 5.000,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 158.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 193.057,75 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 19.305,78 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 212.363,53 |
|
|
|
|
|
|
|
|
|
|
1 |
Bh |
Pemasangan Stop Kontak Inbow |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Tukang Listrik |
|
0,0750 |
OH |
Rp 96.500,00 |
Rp 7.237,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 7.237,50 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Stop kontak |
|
|
1,0000 |
Bh |
Rp 20.000,00 |
Rp 20.000,00 |
|
- |
Inbowdoos seng |
|
|
1,0000 |
Bh |
Rp 1.500,00 |
Rp 1.500,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 21.500,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 28.737,50 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 2.873,75 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 31.611,25 |
|
|
|
|
|
|
|
|
|
|
1 |
Bh |
Pemasangan Stop Kontak AC |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Tukang Listrik |
|
0,0750 |
OH |
Rp 96.500,00 |
Rp 7.237,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 7.237,50 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Stop kontak AC |
|
|
1,0000 |
Bh |
Rp 60.000,00 |
Rp 60.000,00 |
|
- |
Inbowdoos seng |
|
|
1,0000 |
Bh |
Rp 1.500,00 |
Rp 1.500,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 61.500,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 68.737,50 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 6.873,75 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 75.611,25 |
|
|
|
|
|
|
|
|
|
|
1 |
Bh |
Pemasangan Saklar Single |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Tukang Listrik |
|
0,0750 |
OH |
Rp 96.500,00 |
Rp 7.237,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 7.237,50 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Saklar Single |
|
|
1,0000 |
Bh |
Rp 16.000,00 |
Rp 16.000,00 |
|
- |
Inbowdoos seng |
|
|
1,0000 |
Bh |
Rp 1.500,00 |
Rp 1.500,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 17.500,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 24.737,50 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 2.473,75 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 27.211,25 |
|
|
|
|
|
|
|
|
|
|
1 |
Bh |
Pemasangan Saklar Double |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Tukang Listrik |
|
0,0750 |
OH |
Rp 96.500,00 |
Rp 7.237,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 7.237,50 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Saklar Double |
|
|
1,0000 |
Bh |
Rp 20.000,00 |
Rp 20.000,00 |
|
- |
Inbowdoos seng |
|
|
1,0000 |
Bh |
Rp 1.500,00 |
Rp 1.500,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 21.500,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 28.737,50 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 2.873,75 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 31.611,25 |
|
|
|
|
|
|
|
|
|
|
1 |
Bh |
Pemasangan Lampu RM 2 x 18 W with reflektor |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Tukang Listrik |
|
0,0750 |
OH |
Rp 96.500,00 |
Rp 7.237,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 7.237,50 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Amature RM 2 x 18 W includ komponen : |
|
|
1,0000 |
Bh |
Rp 300.000,00 |
Rp 300.000,00 |
|
|
- Lampu RM 2 x 18 W |
|
|
|
|
|
|
|
|
- Balast 18W |
|
|
|
|
|
|
|
|
- Starter S10 |
|
|
|
|
|
|
|
|
- Capasitor |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 300.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 307.237,50 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 30.723,75 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 337.961,25 |
|
|
|
|
|
|
|
|
|
|
1 |
Bh |
Pemasangan Lampu Sl 18 W with Fitting |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Tukang Listrik |
|
0,0750 |
OH |
Rp 96.500,00 |
Rp 7.237,50 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 7.237,50 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Fiting Lampu |
|
|
1,0000 |
Bh |
Rp 10.000,00 |
Rp 10.000,00 |
|
- |
Bolm Lampu |
|
|
1,0000 |
Bh |
Rp 32.000,00 |
Rp 32.000,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 42.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 49.237,50 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 4.923,75 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 54.161,25 |
|
|
|
|
|
|
|
|
|
|
1 |
Bh |
Pemasangan Lampu Sl 18 W with Fitting |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Pekerja |
|
0,3320 |
OH |
Rp 81.500,00 |
Rp 27.058,00 |
|
- |
Tukang Listrik |
|
0,3320 |
OH |
Rp 96.500,00 |
Rp 32.038,00 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 59.096,00 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
MCB 10A 5KA |
|
|
1,0000 |
Bh |
Rp 80.000,00 |
Rp 80.000,00 |
|
- |
Perlengkapan instalasi |
|
|
5% |
|
Rp 80.000,00 |
Rp 4.000,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 84.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 143.096,00 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 14.309,60 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 157.405,60 |
|
|
|
|
|
|
|
|
|
|
1 |
Unit |
Pemasangan Bok MCB |
NO. |
URAIAN |
KOEFISIEN |
SATUAN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
|
- |
Pekerja |
|
0,1083 |
OH |
Rp 81.500,00 |
Rp 8.824,75 |
|
- |
Tukang Listrik |
|
0,0541 |
OH |
Rp 96.500,00 |
Rp 5.224,47 |
|
- |
Mandor |
|
0,0271 |
OH |
Rp 107.000,00 |
Rp 2.896,47 |
|
|
|
|
|
|
JUMLAH HARGA TENAGA |
Rp 16.945,69 |
B |
BAHAN |
|
|
|
|
|
|
|
- |
Box MCB |
|
|
1,0000 |
Unit |
Rp 80.000,00 |
Rp 80.000,00 |
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
Rp 80.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
- |
|
|
|
- |
|
Rp - |
Rp - |
|
|
|
|
|
|
JUMLAH HARGA PERALATAN |
Rp - |
D |
JUMLAH (A+B+C) |
|
|
|
|
|
Rp 96.945,69 |
E |
OVERHEAD & PROFIT |
|
|
10 |
% x D |
|
Rp 9.694,57 |
F |
HARGA SATUAN PEKERJAAN (D+E) |
|
|
|
|
|
Rp 106.640,26 |